Barapukuria - Bogra - Kaliakoir 400 kV Transmission Line Project
Objective(s)• To ensure reliable transmission in Northern Area of the Country
• To ensure power evacuation from proposed Bangladesh-India North-Eastern grid interconnection from Barapukuria.
• To extend High Voltage transmission infrastructure upto northern part of the country for power import from India, Nepal and Bhutan.
Scope of Work1. 400 kV Transmission Line: 260 km.
2. 400kV bay extension: 2 no's
3. 230kV bay extension: 2 no's
Project CostTotal : 336811.45 Lakh Taka
Financed by/DonorLOC (India).
Present StatusPEC Meeting was held on Planning Commission
Estimated DurationJuly, 2018 to June, 2022