National Power Transmission Network Development Project
Objective(s)i. To evacuate power from the proposed 225MW power plant at Sikalbaha
ii. To Provide reliable power to Chittagong city through Rampur & Sikalbaha
iii. To Meet the growing load demand of the areas under the proposed new 132/33 kV substations at Agrabad (Chittagong).; Chouddagram, Ramganj, Bhaluka (Mymensingh), Baroirhat (Chittagong), Benapol, Shariatpur, Barisal-(N), Mahastangarh (Bogra), Jaldhaka (Nilfamari) & Rajshahi-2
Scope of Work1) 230 kV double circuit Transmission Line : 69 km
2) 230 kV u/g Line : 8 km
3) 132 kV Four Circuit In Out Underground Line : 3 km
4) 132 kV u/g Line : 6 km
5) 132 kV double circuit interconnecting line : 139 km
6) 132 kV LILO line : 14 km
7) 230/132 kV Substation: 2 nos.
8) 132/33 kV Substation: 11 nos.
9) Bay Extension of existing Substations
a. 230 kV: 4 nos.
b. 132 kV: 9 nos.
Project CostTotal: BDT 251615.61 Lakh BDT GoB: BDT 80023.53 Lakh BDT Project Aid: BDT 142273.74 Lakh BDT PGCB: BDT 29318.34 Lakh BDT
Development PartnerJICA
Present StatusPhysical:84.98%
Financial: 71.24%

Estimated DurationJanuary, 2013 to December, 2019
Project officeProject Director: Prodip Kumar Sutradhar, Chief Engineer (Addl. Charge)
Address: 17 Mohakhali, Red Crescent Concord Tower (6th floor), Dhaka-1217.
Mobile: 01711620862
E-mail: pd-nptndp@pgcb.org.bd
dpd1-nptndp@pgcb.org.bd (DPD); dpd2-nptndp@pgcb.org.bd (DPD)