Patuakhali -Payra 230 kV Transmission Line Project
Objective(s)The main objective of the project is to supply back feed power to upcoming 1st unit (660 MW) of Payra 1320 MW Power Plant by constructing 230kV line which will be used to make a transmission link to down through a sufficient amount of power in local area from Payra coal power plant in future.
Scope of Work1. To construct 47 km 230kV transmission line.
2. To construct 132 kV Switchyard (except transformer).
3. To extend two 132kV Bay at 132/33 kV existing Substation.
Project CostTotal : 33601.30 Lakh BDT; GoB : 29544.73 Lakh BDT; PGCB : 4056.57 Lakh BDT
Financed by/DonorGoB & PGCB
Present StatusPhysical : 31.80 %
Financial : 18.06 %

Estimated DurationJanuary,2017 to June,2019
Project officeProject Director :Md. Anamul Haque, Superintending Engineer