Bangladesh Power System Security and Efficiency Improvement Project
Objective(s)To address some fundamental measures that must be put in place so that the power system can be operated in a secure and economic manner in line with the longer term goals to deliver much greater quantum of power.
Scope of Work1) Introduction to automatic frequency regulation from NLDC by implementing primary governor control to at least 15 nos. of power generators.
2) Integration of power generators to NLDC network and necessary upgradation of SCADA/EMS core to modernize the dispatch system.
3) Introduction of DLR (Dynamic Line Rating) for 400 km of most important transmission lines of PGCB.
4) Introduction of approximately 800 MVAR Static VAR Compensation (SVC) to critical points of the national grid.
5) Upgradation of few transmission lines capacity either by voltage level upgradation or by reconductoring with higher capacity conductor.
Project CostTotal: 57995.20 Lakh BDT GOB: 9249.84 Lakh BDT PA: 43042.40 Lakh BDT PGCB: 5702.96 Lakh BDT
Financed by/DonorWorld Bank
Present StatusPhysical : 1.00%
Financial : 0.66%
Estimated DurationJuly, 2017 to June, 2021
Project officeProject Director : Md. Abul Kashem, Superintending Engineer
Project Office : NLDC Building , Aftab Nagar, Merul Badda, Dhaka